Published by Jus Connect’s 2023 Industry Insight Report on Construction Arbitration
By Roberta Downey and Marie Devereux
June 29, 2023 • 7-minute read
Contracts in the construction industry often include multi-tiered dispute resolution clauses. These are clauses which set out in an escalating sequence the stages of dispute avoidance and/or alternative dispute resolution (“ADR”) processes that parties would need to go through or follow before referring a dispute to litigation or arbitration. For example, the preceding stages of the Engineer consulting before making a fair determination of a claim and the use of dispute boards set out in the FIDIC suite of contracts before arbitration may be commenced.
When contemplating the use of bespoke dispute resolution provisions or modified versions of standard form clauses, it is important to ensure that the clause, and the process prescribed by the clause, is sufficiently certain to be enforceable. This article considers the use of multi-tiered dispute resolution clauses and their enforceability against the backdrop of the recent case of Kajima Construction Europe (UK) Ltd and another v Children’s Ark Partnership Ltd [2023] EWCA Civ 292.
A clear advantage of multi-tiered dispute resolution clauses is that they impose upon the parties contractual opportunities to cool off and reassess how they might reach a compromise. Such clauses are particularly useful in preventing small disputes from snowballing, saving the parties time and costs, as well as helping them to preserve their commercial relationship.
The trouble arises where one or both of the parties fails to adhere to each of the steps laid out in the clause, and where there is a lack of clarity as to the steps needed to be taken or the mandatory or permissive nature of these steps. There are three common questions: whether the preceding steps are mandatory or optional, the effect of non-compliance and whether or not the clause is enforceable. This article will focus on the third question.
Historically, the English courts have treated agreements to negotiate or to resolve a claim by friendly discussions with suspicion. An agreement to the effect that parties shall “strive to settle [disputes] amicably” or that parties must first be “unable [to] reach amicable settlement” before referring a dispute to arbitration was held not to be a legally enforceable obligation (See, Itex Shipping v China Ocean Shipping [1989] 2 Lloyds Rep 522 and Paul Smith v H&S International Holding [1991] 2 Lloyds Rep 127). The House of Lords in Walford v Miles [1992] 2 AC 128 confirmed that a bare agreement to negotiate was too uncertain to be enforceable and likened such a clause to an agreement to agree.
The introduction of pre-action protocols with Lord Woolf’s reforms to the Civil Procedure Rules in 1999 (“CPR”), heralded increasing intervention by the Courts in forcing parties to consider mediation and go through a cooling-off process in which they must set out their positions clearly and meet before running off to court (See, CPR 1.4).
Against this backdrop, courts have expressly recognized the public interest benefit of giving effect to multi-tiered dispute resolution clauses: first, as a reflection of the commercial arrangement struck by the parties when they entered into the contract, and second, because such clauses provide well-timed opportunities for the parties to resolve a dispute in a cheaper, quicker and less antagonistic way.
In Cable & Wireless Plc v IBM United Kingdom Ltd [2002] EWHC 2059 (Comm), the Court found that a provision requiring parties to participate in an ADR procedure recommended by the Centre for Effective Dispute Resolution (“CEDR”) before commencing litigation was an enforceable obligation. Colman J said the clause was certain enough to be enforceable because it did not merely prescribe a good faith attempt to negotiate a settlement; it also identified a particular procedure the parties needed to follow.
Nevertheless, in keeping with the fundamental rules of contract interpretation, clarity and certainty remain key. Where Courts have found that provisions have simply been too uncertain to create an unenforceable obligation, they have not hesitated to make such a finding:
In the recent case of Children’s Ark Partnerships Ltd v Kajima Construction Europe (UK) Limited, at first instance (See, [2022] EWHC 1595 (TCC)), Joanna Smith J emphasized that the overarching requirement for a dispute resolution procedure to be enforceable is that the provision must be “sufficiently clear and certain by reference to objective criteria” (See, [59]). The Court considered the requirements identified in earlier authorities, namely:
On the facts, Children’s Ark Partnership (“CAP”) entered into an agreement with a hospital trust to redevelop a children’s hospital, and on the same day, entered into a construction contract with Kajima for the design, construction and commissioning of the hospital (the “Contract”). The Contract adopted the following dispute resolution procedure (“DRP”) provision:
CAP issued an application to stay court proceedings so that it could carry out the DRP before its limitation period to bring claims expired. Kajima applied to strike out or set aside that application arguing the DRP provision was a condition precedent to commencing court proceedings.
Joanna Smith J agreed with Kajima: she found that the obligation to refer disputes to the Liaison Committee was not defined with sufficient clarity and certainty, such that it could constitute a legally effective precondition to the commencement of proceedings.
On appeal (See, [2023] EWCA Civ 292), the Court of Appeal agreed the DRP was simply too uncertain to be enforceable. Coulson LJ gave the leading judgment, finding it was salient that:
There was an additional judgment from Popplewell LJ, which agreed with the unenforceability of the DRP but on a much narrower basis. He said that the only aspect of the DRP rendering it unenforceable was the uncertainty as to how and when the DRP process was complete. Popplewell LJ’s dicta emphasized the weight which Courts place on contractual autonomy and noted that Courts are reluctant to hold that an agreement is void for uncertainty and will only do so as “a last resort”. He considered that there was a sufficiently certain process in place, which depended not on further agreement between CAP and Kajima, but upon the procedure the Committee decided to adopt.
While there is no established test as to what makes a multi-tiered dispute resolution provision enforceable and each case will depend on the facts, Kajima Construction Europe (UK) Ltd v Children’s Ark Partnership has helpfully identified and distilled key principles, which contract-drafters would do well to bear in mind:
This information is provided by Vinson & Elkins LLP for educational and informational purposes only and is not intended, nor should it be construed, as legal advice.
Discover our latest:
Events
Jenny Speck to Speak at Lockton U.S. Energy Risk Summit
Partner Jenny Speck will speak at Lockton’s U.S. Energy Risk Summit on November 12, 2026, in Houston, Texas. The summit …
November 12, 2026
November 12, 2026 • 1-minute read
CLE Events
Sixth Annual Navigating the Annual Meeting and Reporting Season
Join leading practitioners and industry voices for a timely discussion of the legal, regulatory, and governance developments shaping the next proxy season.
November 11, 2026
November 11, 2026 • 2-minute read
Events
Jenny Speck Speaking at 2026 AFCC Global Biobased Economy Conference
Partner Jenny Speck will speak at the 2026 AFCC Global Biobased Economy Conference & Exhibit in a session titled “Tax …
November 3, 2026
November 3, 2026 • 1-minute read
Podcasts
Powering Progress Episode 14 – Environmental Litigation and the New Data Center Playbook
This series has explored the extraordinary investment flowing into data centers and the challenges surrounding power, real estate, financing, and …
October 29, 2026
October 29, 2026 • 14-minute read
Client Alerts
UK Budget 2026: Data Centres and Power Generation
The Chancellor, John Healey, promised to tackle “the big challenges in energy” with a 10 Year Plan. The Government’s headline …
October 28, 2026
October 28, 2026 • 4-minute read
Thoughts or questions? Send us a note, and we’ll connect you with the right person.